French Firm EDF Submits Fresh Proposal for JNPP to NPCIL

A French firm, EDF submits a fresh plan to build six atomic reactors, each with a capacity of 1650 MW each some 500 km south of Mumbai  at Jaitapur to the NPCIL proposing to share a larger role in the engineering aspect of the project, a top executive of the company said.

A construction of a nuclear plant is usually discussed in terms of the EPC (Engineering, Procurement and Construction). The EDF has proposed to take care of the engineering part and a large chunk of the procurement of equipment which have to be sourced from abroad, the official said.

When operational, the proposed plant will be the largest nuclear power generation park in the country.

EDF, and the NPCIL have also resolved to sign the General Framework Agreement (GFA) for the Jaitapur Nuclear Power Plant (JNPP) by the end of the year.

French President Emmanuel Macron is likely to visit India by the year-end and the two sides are working to fast track the negotiations so that the GFA could be signed during that time, the EDF official, who did not wish to be quoted, said.

EDF delegations also meet officials of the Prime Minister’s Office and the Ministry of External Affairs to discuss the issue.

However, the EDF insists that the Nuclear Power Corporation of India (NPCIL) should take care of the construction part as it has an experience of building the Kudankulam Nuclear Power Plant (KKNPP).

The NPCIL, on the other hand, wants the EDF to take the full responsibility of the EPC, citing the reason that the EPR technology is new to India.

A senior Indian government official, pointed out that the GFA hinges on three aspects — lower tariff, credit and a functional reference plant.

Discussions are on between the Ministry of Finance and the French Treasury Department on matter related to credit. Some part of it will be in euros while the rest will be in rupees, the EDF official said.

The Flamanville EPR nuclear power reactor, which has been shown as a reference plant for the JNPP, is expected to be commissioned by 2018.